Process :
Prep
Asbestos ( test and abatement in case )
Demolition and Shoring in case
Foundation after Footing
Concrete job with inspection
Framing
Electric
Plumbing
HVAC
Boiler and piping - Rough Inspection
Sheating and Windows and Doors
Window, door molding
Partition wall and Inside Doors
Water proofing
Outside wrapping Brick or Metal finish
Siding finish
Roof
Bathroom and Kitchen
Gate
Fence
Tree
Gardening
Inspection
Completion
Before :
Initial discussion with customer : 1 month [ 3-6 month or so including Banking industry ]
Architect Drawing 1-3 months
New Building 3 -18 months
Renovation 1-2 months
Extention with Structure design : 2-4 months
.. the lead time of customer contact and modify ....1-2 months or more
DOB contact / Examiner : 1-3 months
Filing : Self or regular : 1-3 months
GC contract : RFP / Estimate / Proposal / RFI / Submittal
sub contractor contact and contract : 1-3 months or 1-2 weeks
Main Contract : AIA or others : 2-4 weeks
Plan approved and each work permit : 1-2 months
Job Start : :::::
Process :
Prep
Asbestos ( test and abatement in case )
Demolition and Shoring in case
Foundation after Footing
Concrete job with inspection
Framing
Electric
Plumbing
HVAC
Boiler and piping - Rough Inspection
Sheating and Windows and Doors
Window, door molding
Partition wall and Inside Doors
Water proofing
Outside wrapping Brick or Metal finish
Siding finish
Roof
Bathroom and Kitchen
Gate
Fence
Tree
Gardening
Inspection
Completion
Before :
Initial discussion with customer : 1 month [ 3-6 month or so including Banking industry ]
Architect Drawing 1-3 months
New Building 3 -18 months
Renovation 1-2 months
Extention with Structure design : 2-4 months
.. the lead time of customer contact and modify ....1-2 months or more
DOB contact / Examiner : 1-3 months
Filing : Self or regular : 1-3 months
GC contract : RFP / Estimate / Proposal / RFI / Submittal
sub contractor contact and contract : 1-3 months or 1-2 weeks
Main Contract : AIA or others : 2-4 weeks
Plan approved and each work permit : 1-2 months
Job Start : :::::